Building Construction Update – Kolkata The brick work and RCC slab for all the seven floors of Wing-B has been completed. Plastering, tiles, plumbing and sanitation, OHT, Lift and other […]
Category Archives: New Building Construction
The brick work in the seven floors of Wing-B is almost completed. Plastering, tiles, plumbing and sanitation, OHT, Lift and other works are underway. The total cost incurred for Wing […]
The total cost incurred for Wing B construction till date amounts to Rs. 8.38 Crores. So far, the brick work upto the 4th floor has been completed. In Wing-A, the […]
The total cost incurred for casting concrete slabs on six floors of Wing B amounts to 6.88 Crores. In Wing-A, the foundation is partially done at a cost of Rs. […]
The fourth-floor slab of Wing-B has been cast on 25/6/2023. The remaining three slabs are expected to be cast before Durga Puja. The expenditure of about Rs. 7.5 crore has […]
Dear Donors, Friends and Well-wishers, You are aware that the construction work of Advaita Ashrama’s new building in Kolkata had commenced in the month of May 2022. In the last […]
Concrete Slab casting is completed on the First Floor of Wing B. Here are some pictures:
Dear Donors, Friends and Well-wishers, You are aware that the construction work of Advaita Ashrama’s new building in Kolkata had commenced in the month of May 2022. In the last […]